Exact fees, review timelines, portal links, and step-by-step instructions for getting an EV charger permit in major U.S. cities.
DevelopmentATX portal · $75–$150 · 3–10 days review · 1–3 weeks total
OneStopHouston · $75–$175 · 5–14 days review · 1–2 weeks total
Nashville.gov permits · $75–$150 · 5–14 days review · 2–3 weeks total
City of Phoenix Online · $75–$175 · 7–14 days review · 2–4 weeks total
Denver eDevelopment · $100–$200 · 5–10 days review · 1–3 weeks total
CLT Development portal · $75–$150 · 5–10 days review · 2–3 weeks total
Atlanta One-Stop Shop · $75–$175 · 7–14 days review · 2–4 weeks total
Seattle Services Portal · $100–$200 · 3–7 days review · 1–3 weeks total
Columbus Building Services · $75–$175 · 5–14 days review · 2–4 weeks total
Clark County Online · $100–$200 · 7–14 days review · 2–4 weeks total
Portland Online ePlans · $100–$175 · 5–10 days review · 2–3 weeks total
Miami-Dade Building Dept · $100–$249 · 7–21 days review · 3–5 weeks total
Browse our state-by-state guides for permit requirements in your area, or use the free permit checker tool for a personalized assessment. More city guides are added regularly.